Cleanup in the Upper Clark Fork began in 2010 and is proceeding in phases (from 1 to 22 according to the 2023 Strategic Plan). Current developments are described below. For more information also see our February 2025 and May 2025 newsletters.

CONSTRUCTION COMPLETED: December 2025
PRELIM TOTAL COST: $5.6 million (incl. monitoring, maint, reveg, etc.)
NEXT STEPS: Design/build new wetlands; Public tour, summer 2026
______________________
LOCATION & DESCRIPTION: (See cleanup design & related docs HERE.)
A 40-acre site ~10 miles south of Deer Lodge to the east of Racetrack Pond, running 2.2 river miles SW to NE beginning just north of Gemback Road.
CHARACTERISTICS:
Relative to other phases, the Strategic Plan characterized Ph. 7 as "Moderate Priority" for erosion of contaminated sediments into the river; and "High Priority" for contaminated soil levels, as the area includes a public fishing access (pp.11-12). DEQ estimated removal of 135,800 cubic yards of mine waste-contaminated material from the site.
STATUS (as of May 2026)
Construction was completed in Dec. 2025, and the parking lot, stated-owned portions of the floodplain, and the river are now open to the public. (If you visit the site, please do not trespass on private property and be aware of tripping hazards.) The project cost ~$5.6 million, including construction, engineering, revegetation, streambank material, and surveying. This total is over original estimates, as more contaminated material needed to be removed (173,250 cubic yards total), which also required more backfill. Costs and lessons learned from Phase 7 will inform the State's upcoming updates to its 2023 CFROU Strategic Plan. NEXT STEPS: As of May 2026 DEQ was finalizing some minor repairs to revegetated areas and adjacent private lands due to impacts from heavy equipment. Design of a new wetlands feature on the east side of the site (which will reclaim some borrow areas and provide diverse waterfowl habitat in the area) is also underway, with construction estimated to start in fall 2026. CFRTAC is currently reviewing and providing input on the wetland design, and will participate in a public tour of Ph 7, on June 16, 2026.
See our comments on Ph.7 design here, the State's response to comments here, and more info on Ph.7 in our February and May 2025 newsletters.

ESTIMATED START DATE: No start date currently estimated
ESTIMATED TOTAL COST: $20.62M (may change)
______________________
LOCATION & DESCRIPTION:
Includes Arrowstone Park. Extends through Deer Lodge from the I-90 bridge at Exit 187 (eastbound) north to the city's boundary with Grant Kohrs Ranch (near the Cottonwood Creek confluence).
CHARACTERISTICS:
This phase is of high concern because temporary soil caps installed ~30 years ago at Arrowstone Park are failing in some areas, exposing arsenic and other contaminants that have created public health risks. As noted in DEQ's 2024 Clark Fork River News, community concern led DEQ to prioritize cleanup here. In the interim, DEQ installed safety signage and added temporary soil caps on bare spots to cover exposed toxic contaminants.
STATUS (as of May 2026):
Additional sampling is needed at the site to fill data gaps, including examining soils at greater depth in some areas and sampling areas that DEQ previously did not have access to. DEQ and EPA also want to conduct additional surface-level sampling in some areas to have more up-to-date data; to better factor in current use of the park (to ensure focus is on the highest-use areas); and to apply more up-to-date sampling methodologies than were used previously.
The final sampling data will help determine contamination removal boundaries and depths, which is necessary before cleanup design can begin. DEQ and EPA are now finalizing a sampling plan and Quality Assurance Plan (QAP), and estimate the additional sampling at Arrowstone Park will take place in the 2026 field season. The final QAP will also be added to the sampling plan for Phases 10-12.
As this work continues, the public is advised to obey caution signs at the park, avoid areas with exposed soil, and wash hands, boots, pets, boats, etc. after any potential exposure to contaminated soils, especially on the river banks.

COMPLETED PHASES (maintenance & monitoring underway):
__________________
NEXT UP AFTER PHASE 7 & PHASE 13/14 (described above):

Phases 7 and 10-14 (described above) were prioritized for cleanup based on the ranking criteria described on p. 12 of the 2023 Strategic Plan. Other phases will be addressed in an upstream-to-downstream sequence after these higher-priority phases are completed. These include: